Offshore windfarms

Scottish Power Renewables (SPR) is in the pre-application phase for two new offshore wind farm projects in the East Anglia zone. They are currently in the construction phase of East Anglia One (granted consent by the Secretary of State in June 2014) and the post-planning phase of East Anglia Three (granted consent by the Secretary of State in August 2017).

East Anglia One North

The project is located approximately 36km from Lowestoft in an area of 209km² with a potential generating capacity of up to 800 megawatts.

More on East Anglia One North from SPR

East Anglia Two

The project is located approximately 31 km from Lowestoft in an area of 255km² with a potential generating capacity of up to 900 megawatts. 

More on East Anglia Two from SPR

The district and county councils are taking a joint local authority approach to the proposals and where possible responding jointly.

The proposals are being dealt with as two Nationally Significant Infrastructure Projects. There are proposed to be six key milestones in the planning phase of the proposals: they are currently running simultaneously but this may change in the future:

  • Phase 1: Informal Public Information Days (PIDs) - Completed
  • Phase 2: Formal PIDs - Completed 17 April 2018
  • Phase 3: Formal PIDs - Completed 28 August 2018
  • Phase 3.5: Formal PIDs - Completed 12 November 2018
  • Phase 4: Formal PIDs - Not yet determined

Submission of Development Consent Order (DCO) to the Secretary of State – the DCO will be developed following the refinement of proposals from the consultation phases. The Planning Inspectorate will lead an assessment of the proposals. The local authorities are stakeholders in the process and not the determining authority.

Decision by the Secretary of State – following its assessment, the Planning Inspectorate will make a recommendation to the Secretary of State. The Secretary of State will make their final decision within three months of receiving the recommendation.

We responded to the Planning Inspectorate in relation to the Scoping Opinion:

The first phase of public consultation (Phase 2)  took place in March/April 2018:

The second round of public consultation (Phase 3) took place between May and August 2018:

The third round of public consultation (Phase 3.5) began on 29 September2018.

On 17 October, together with Suffolk County Council, we sent a joint letter to Scottish Power Renewables, requesting an extension of the consultation period by two weeks in Phase 3.5 for East Anglia One North and East Anglia Two offshore windfarms.

Scottish Power Renewables listened and extended the consultation deadline for each proposal from 29 October to 12 November 2018.

A joint letter, signed by the Leaders of the District and County Councils has been sent to the Secretaries of State for Business, Energy and Industrial Strategy and Housing, Communities and Local Government, having regard to all energy projects in the East Suffolk locality.

To contact the Council's Planners, email our Development Management Team with the reference "East Anglia 1 North and 2 Offshore Windfarms".